VAXft Systems Model 810 Installation Information

*HyperReader

  CONTENTS

  Title Page

  Copyright Page

  1      System Inspection and Unpacking

  1.1     In This Chapter

  1.2     Unloading the System

  1.3     Inspecting the Shipment

  1.4     Moving the Shipment

  1.5     Unpacking the Options

  1.6     Opening the Shipping Cartons

  1.7     Unpacking the Cabinets

  1.8     Deskidding the Cabinets

  2      Cabinet Assembly and Cable Installation

  2.1     In This Chapter

  2.2     Entry System Interface Cabling

  2.3     Entry System Power Cabling

  2.4     Expanded System Cabinet Preparation

  2.5     Expanded System Cabinet Assembly

  2.6     Expanded System Interface Cabling
    2.6.1      DSSI and Ethernet Configurations

  2.7     Expanded System Power Cabling

  3      Completing the System Installation

  3.1     In This Chapter

  3.2     Power Preparation Procedure

  3.3     Turning On System Power

  3.4     Turning Off Zone and System Power

  3.5     Setting the Terminal Baud Rate

  3.6     Final System Tests

  A   Cabinet and Component Descriptions

  A.1     In This Appendix

  A.2     CPU and Expansion Cabinets

  A.3     Zone Control Panel

  A.4     Power Modules

  A.5     Domestic and International Power Distribution Boxes

  FIGURES

  1-1        Opening a Cabinet Shipping Carton

  1-2        Unpacking a Cabinet

  1-3        Attaching the Deskidding Ramps

  2-1        Console Module Connectors

  2-2        Cabinet Panels

  2-3        Assembling the Cabinets

  2-4        DSSI Cabling Example 1

  2-5        Card Cage Cabling for Example 1

  2-6        Zone A and B Interface Module Card Cages

  2-7        Device and Cable Locations

  2-8        Console Module Connectors

  2-9        DSSI Cabling Example 2

  3-1        Power Module Controls and Indicators

  A-1        Cabinet Layout, Front View

  A-2        Cabinet Layout, Rear View

  A-3        Zone Control Panel

  A-4        Power Module Controls and Indicators

  A-5        Domestic Power Distribution Box

  A-6        International Power Distribution Box

  TABLES

  1-1        Inspecting the Shipment

  1-2        Moving the Shipment

  1-3        Unpacking the Options

  1-4        Opening the Shipping Cartons

  1-5        Key to Figure 1-1, Opening a Cabinet Shipping Carton

  1-6        Unpacking the Cabinets

  1-7        Key to Figure 1-2, Unpacking a Cabinet

  1-8        Deskidding the Cabinets

  1-9        Key to Figure 1-3, Attaching the Deskidding Ramps

  2-1        Entry System Interface Cabling

  2-2        TA85 Tape Drive Cabling

  2-3        Power Cable Country Kits

  2-4        Preparing the Cabinets for Assembly

  2-5        Key to Figure 2-2, Cabinet Panels

  2-6        Assembling the Cabinets

  2-7        Key to Figure 2-3, Assembling the Cabinets

  2-8        Supported Device Nodes

  2-9        Summary of Example 1 DSSI Cabling Rules

  2-10       Detail of Example 1 System Interface Cabling

  2-11       Example 1 System Power Cabling

  2-12       Power Cable Country Kits

  3-1        Power Preparation Procedure

  3-2        Turning On System Power

  3-3        Key to Figure 3-1, Power Module Controls and Indicators

  3-4        Turning Off Zone Power

  3-5        Turning Off System Power

  3-6        Running Final System Tests

  A-1        Key to Figure A-1, Cabinet Layout, Front View

  A-2        Key to Figure A-2, Cabinet Layout, Rear View

  A-3        Key to Figure A-3, Zone Control Panel

  A-4        Key to Figure A-4, Power Module Controls and Indicators

  A-5        Key to Figure A-5, Domestic Power Distribution Box

  A-6        Key to Figure A-6, International Power Distribution Box